Cambridgeshire County Council has clarified why residents were told controversial fencing being installed along the Busway in H&I was ordered months before the scheme had been formally approved.
The fencing, estimated to cost £6.58 million, is being rolled out along the entire 25km stretch of the Busway. The County Council says it is necessary for Health and Safety, as the Busway is managed as a workplace rather than a typical public road.
Informal crossing points
At a public meeting last month, the Council assured residents that wooden posts with wire were being considered for the Busway fencing design. However, tall green palisade fencing appeared days later to block informal crossing points long used by residents to access nearby green spaces.
During a follow-up Council drop-in session on Tuesday night (October 21), officials there allegedly told residents that the fencing had been in the works since the start of the year – well before Councillors approved the project in the summer.

H&I County Councillor Ros Hathorn said: “At last month’s public meeting, everyone was told the fencing would not yet be installed along the Busway in Histon and Impington. Within a matter of days, we have this tall 2.4m palisade fencing with spikes going up. I still don’t understand why it wasn’t explained to us that this was going to be happening.
“The Council has prioritised fencing off the informal crossing points, and I find it astonishing that its first effort to address the situation is to completely close them off with imposing spiked fencing, rather than starting with signage or other approaches first.”
David Mail, who also attended Tuesday’s drop-in, said he was told a different Cambridgeshire County Council department had already chosen the green fencing before the September public meeting, but hadn’t informed the officers presenting at it.
Two fencing types
As the confusion emerged this week, Cambridgeshire County Council this morning (Thursday) explained two types of fencing are being installed along the Busway. The decision by Councillors in June was “related to the permanent fencing which will separate the Busway and the path along the whole Busway”.
The other fencing – described as “perimeter fencing” – is being used to block off informal crossing points. This would have been ordered before Councillors approved the other 25km fencing scheme as part of the Busway’s maintenance – and is being installed now “for Health and Safety reasons”.
Ros added: “I do feel there has been a severe lack of transparency at many levels when it comes to this issue as a whole – but what I will say is that the Council is finally beginning to address this.
“Tuesday’s drop-in session was a good opportunity for everyone to speak directly to the officers on this project about the issues that matter to them. Each officer was talking directly to people using their own experience and role in the Council, consequently I got the impression from public commentary that the same question being asked did not always elicit the same response.”
Mixed messages

Tuesday evening’s drop-in session was held at Histon Baptist Church and the County Council says almost 100 people attended. One topic raised at the session was whether the fencing already installed could be removed if any of the informal crossings were eventually made public rights of way. Residents reported conflicting answers.
One said they were told the fencing would remain permanently. Another claimed they were informed that currently informal crossings – including those at the Orchard and Manor Field – could potentially be reinstated.
The resident added: “If it goes ahead [the crossing] will have to be flat, like St Audrey’s and not like the crossing between Northstowe and Rampton. [This] arguably is safer as you’re forced to stop and negotiate the beams. You can’t cycle across beams so [you] have to dismount if on a bike.”
The online discussion between residents was also critical of the Council’s Health and Safety Risk Assessment for the Guided Busway, which was made public before the drop-in session. The methodology and level of detail was questioned, and another resident mentioned they were told it was possible the wrong version had been posted online. Ros has invited residents to address any concerns directly with the Council.
Crossing points
Visitors to the drop-in session were also presented with the results of an online survey which has captured how often residents use the informal crossing points. It revealed that crossings at The Orchard, Manor Park, and St Audrey’s are used most frequently in H&I – often weekly – mainly for walking, exercise, and dog walking. The least-used crossing was identified as the one between the Holiday Inn and Station Road in Impington.

While hundreds described how they use the crossings to access green space, some more personal concerns were also raised. One person said: “The fences blocking access and along the Busway will make me feel less safe especially with the problems lately with anti social behaviour.”
Meanwhile, a Council document shared at the session explained there are 23 regularly used informal crossings along the Busway – all of which are now being closed under the current fencing scheme.
It said: “The closure of the informal crossing points is necessary to meet the Council’s statutory responsibilities in relation to Health and Safety on the Busway which unlike other roads is managed as a workplace.
“Consideration will be given to opening new formal crossings on the Busway, and if the case for such provision is made and funding is available, works will then be undertaken to provide a safe new or reopened crossing.”
Bridges ‘visually intrusive’
The document also explained that the option of bridge provision “would be prohibitively expensive and could be visually intrusive in the landscape”. It added the formal “at-grade crossing facilities” involve “significant engineering works” and cost in the region of £500,000.
The document said: “The cost of provision is not in itself a reason for such provision to be ruled out, but it could constrain the ability of the County Council to programme works until funding were available and agreed by the Council’s Highways and Transport Committee.”
The Council spokesperson added: “We understand people’s frustrations about the fencing, but people must keep to the formal crossing points for their own safety. We will continue to review, and risk assess the Busway as the safety improvement works progress.”
She also said another public meeting is being organised for next month.
For more information about the Busway fencing, visit the Cambridgeshire County Council website.
READ MORE: Meeting releases residents’ anger over imminent Busway fencing


This really needs escalating to parliament and the BBC. HSE are the completely the wrong organisation to have jurisdiction over the busway and to class it as a “Factory”. Fencing off these extremely useful crossings while leaving the 2m pinchpoint unaddressed for 13 years is symptomatic of the municipal dysfunction over the busway. HSE also think having buses on permanent fullbeam “far safety” is a good idea even though it dazzles cyclists on dark winter evenings. Could be straight from a Yes Minister episode in the 1980s.