Contractors set to smash A14 re-opening targets

-

Highways England’s announcement of an early finish to A14 roadworks stands to bring some relief from the traffic chaos for our village, but the Busway closure continues. Liz Hill reports.

Traffic chaos through Histon and Impington, caused by roadworks on the A14, is set to end more than six months earlier than planned. The improved road was scheduled to open to traffic by the end of 2020. The scheme is now due to open in April this year, though no specific date has yet been given.

As well as road widening and junction improvements, the scheme will provide a new local access road, the A1307. This will run parallel to the A14 between Cambridge and Godmanchester, serving the surrounding communities. There will also be new routes for cyclists, walkers and horse riders.

The A14 re-opening will mark the end of permanent roadworks and reduced speed limits on the road between Swavesey and Milton, though landscaping, installing some new technology and work in the verges will continue beyond that date. Some temporary overnight closures or off-peak daytime lane closures will still be needed.

Busway woes continue

In the meanwhile though, delays to the re-opening of the Guided Busway continue. As part of the work to upgrade the A14, the bridge at Impington near Histon is being widened. The work has proved more challenging than expected and projected completion dates have consistently been missed. The Busway was due to reopen this week, but the new anticipated re-opening date is early March.

Bus, cycle and walking routes into Cambrdige will continue to be diverted, though the resurfacing of part of the Junction 32 roundabout and one of the slip roads should soon enable the cycle and footpaths on both sides of the roundabout to be re-opened.

Re-planting plans

Highways England has committed to creating over a hectare of new, connected habitat for wildlife and planting more than 900,000 trees and shrubs around the upgraded A14 – two for every one removed before work started. But Histon and Impington Councillor Pippa Heylings is asking for confirmation of plans specifically around Junction 32 at the entrance to the village.

She said: “Part of these finishing works includes landscaping – which is very important for Histon, Impington and Orchard Park to help restore as much as possible the green gateway to the village and provide a small level of protection from noise and air pollution. Together with the Landscaping Group – your councillors, SCDC & Highways – and HI Trees, there are potentially good plans for re-planting and landscaping on all sides of the junction, including species that are helpful in filtering air pollution; and the establishment of a biodiverse-rich area around an enlarged attenuation pond.”

More jams ahead

The A14 improvement scheme will improve East/West journeys passing by the village, but traffic jams are likely to continue for those heading into Cambridge. The opening of the A14 improvements will coincide with the closure of the B1049 Histon Road into Cambridge. Whilst remaining open to traffic pedestrians and cyclists going in both directions, those travelling into Cambridge on this route by motor vehicle will face diversions.