A withering report by the Local Highways Authority reveals that developer McCarthy & Stone has ignored pre-application advice on the maximum number of properties that would be allowed on the Barrel Field site.
McCarthy & Stone, the developer hoping to a build a retirement village on land being sold by jam factory owner Hain Daniels, has been knocked back by the Local Highways Authority.
The company had asked the Authority to give pre-application advice on a development of 91 residences, and its attempt to squeeze an additional 14 properties onto the Barrel Field site has fallen foul of planning rules.
Fundamental to the Highways Authority objections is that the scheme now being put forward by the developer has “failed to provide two points of access into the development as required for any development over 100 dwelling units.” The extra properties that have been included in the planning application they submitted, break the rules that require a second 3.75m access route onto the site for emergency vehicles, cycles and pedestrians.
Alternatives?
The constraints of the Barrel Field site and the ownership of surrounding land appear to make a second access route impossible, unless Hain Daniels were to open up more of its own land to allow residential traffic through the factory grounds and negotiate an exit through Chivers Way on Vision Park, which is a private road. The main alternative would be for McCarthy & Stone to reconfigure its plans to create access through Saffron Road – something that residents are likely to strongly oppose given the traffic issues there already.
The community has been arguing from the start that using Home Close as the single access route onto the site would place a huge strain on the local road and network and cause serious parking, traffic and access issues. The concerns raised by the Highways Authority are on safety grounds, and it is unclear how the plans in their current form could be approved by planners, though the final decision lies with South Cambs District councillors.
Other conditions
The Highways Authority went on to explain that the developer would have to meet a series of conditions if planning permission were to be given. These include creating an access road onto the site with a 2m footpath on each side, and providing details of the number, location and design of secure cycle parking and storage that must be “at least as convenient as access to car parking”.
Because the roads within the new retirement village would not be adopted by the Highways Authority, they are also concerned about drainage from the site. They have told planners that, if they were to approve planning permission, the proposed access must be built so that no private water from the site would drain across or onto any adopted public highway. They point out that the ‘permeable paving’ proposed by the developers is not sufficient to guarantee that, and are demanding that “physical measures” would have to be put in place.
The Lead Local Flood Authority has also objected to planning permission being granted and has highlighted inadequacies in the drainage plan for the site, including the implications of chemical and asbestos contamination in the ground.
Last chance to have a say
Due to problems with the Greater Cambridge Shared Planning web portal, the deadline for local residents to add their voices to the consultation about the McCarthy & Stone proposals was moved to Friday 19 February. Comments can be submitted online, and anyone frustrated by outages on the planning portal can make their submission in writing.
Read also: Act now to protect the village from over-development, says Parish Council ; Objections build around proposed retirement development ; Access issues provoke angry reaction to development plans ; 100 retirement homes to be built beside the Community Orchard
Full details of the Mc Carthy & Stone planning application (Ref: 20/05145/FUL) are available online here until 19 February when the consultation closes.
Responses to it can be submitted online here or in writing to Planning Officer David Norris, South Cambridgeshire Hall, Cambourne Business Park, Cambourne, Cambridge CB23 6EA.
Comments not submitted online should be copied to South Cambridgeshire District Councillors and to Histon & Impington Parish Council.
Pippa Heylings (Planning Committee Member) cllr.heylings@scambs.gov.uk
Martin Cahn (Planning Committee Member) cllr.cahn@scambs.gov.uk
Steve Hunt (Council Member for Histon & Impington) cllr.hunts@scambs.gov.uk
Histon & Impington Parish Councilhelpdesk@hisimp.net